Dream house – Part 4 (Construction)


Quick Recap

Getting here took a while and things in a very specific order. I did not not need to do the site prep myself, but I did and it was fun(kind of?). Large items in order:

  • Electrical
  • Septic design
  • Site plan design
  • Well
  • Construction marker survey. Shortly after, the site was vandalized and markers removed from the ground.
  • Permits. The county FPB (incorrectly) stated the driveway grade was too steep and required further designs, which was proven to be within compliance. We were also not quite happy with the house location at this phase and therefore we needed to have a new septic design, updated site+drainage plan, and new survey. This required resubmitting numerous documents and $$$$.
  • Construction loan. These are not easy to get.

Land clearing

The day is finally here. We started with removing stumps on 06/20/2024 and clearing a path to the drain field location. After that, the remaining area was cleared.

Excavating

With clearing complete, it’s time to start digging for the foundation. First moments were captured on video! Worked started 07/09/2024. It was 98F out, which made the experience not enjoyable.

Here’s a partial timelapse of the work

Foundation

Footings

Pouring the footing took two cement trucks. Pouring took place 07/24/2024.

Here’s a time lapse of the pour. I arrived a bit late; I did not capture the beginning.

Walls

Forms and pouring of the walls. The forms were stripped over the next 48 hours. The back walls were initially supposed to be 24″ tall with 24″ pony walls, but the county engineer would not permit this. We had to step up all walls to 48″ concrete.

Backfill

After the concrete, backfill and drainage pipes are installed. These include a foundation drain and downspout drains.

Framing

First lumber drop arrived 08/21/2024. The truck broke down delaying the delivery. The flooring was not expected in the first drop.